Supply Chain Actions

You use this program to identify suggested supply chain transfers that require corrective action to meet the planning indicated within the snapshot files.

Report Options

Field Description
Print options  
Print pegging Select this to print the pegging information on the report.
New page per stock code Select this to print the information for each stock item on a different page.

Selection criteria

Field Description
Stock code selection Indicate the stock code(s) for which to include supply chain transfers in the report.
Target warehouse selection Indicate the target warehouse(s) for which to include supply chain transfers in the report.
Buyer selection Indicate the buyer(s) for whom to include supply chain transfers in the report.
Due date selection Indicate the due date(s) for which to include supply chain transfers in the report.
Product class selection Indicate the product class(es) for which to include supply chain transfers in the report.
Planner selection Indicate the planner(s) for whom to include supply chain transfers in the report.

Actions and Exclusions

Field Description
Action selections Indicate suggested and live supply chain transfers according to the action messages displayed against them.
Change Select this to include live supply chain transfer orders that should be changed.

The criteria for suggesting changes are based on differences between ship dates and/or due dates of the live SCT and the snapshot files.

Delay Select this to include live supply chain transfer orders that should be delayed.

These are supply chain transfers taking place too early to meet the demand. The current transfer due dates precede the demand dates.

Cancel Select this to select all live supply chain transfers with a suggested delivery date later than 01/01/2045.

The Requirements Calculation program re-schedules supply chain transfers (for which there is no demand) to beyond this date.

New

Select this to select suggested supply chain transfers that should be converted into a live supply chain transfer order.

When you select only this option, the report includes only suggested supply chain transfers (i.e. no live supply chain transfers are included).

Include transfers with no action Select this to include transfers against which no action is defined.
Exception selections Indicate suggested and live supply chain transfers according to the exception messages displayed against them.
Late Select this to include transfers identified as late.
Overdue Select this to include transfers identified as overdue.
Include transfers with no exception Select this to include transfers that are not late or overdue.
Exclude actions  
Less than (days) The transfer is excluded from the report if the number of days by which a transfer must be rescheduled is less than the entry made here.

Output Options

These options enable you to apply a theme to the report and to define multiple output destinations for the report once it has been compiled (SRS Output Options).

Report Details

The program compares information residing within the snapshot files to information residing within the live files and reports on the differences.

The Requirements Calculation program generates the planning indicated within the snapshot files.

A supply chain transfer is both a demand (from the target warehouse) and a supply (from the source warehouse) for the same stock item.

The report includes any quantity that has been dispatched but not invoiced for a Supply Chain Transfer sales order as part of the supply for the item in the target warehouse.

The latest requirements calculation date is printed on each report.