Initial Build Extract
You use this program to create a build schedule file by extracting any MPS items from both the forecast file and/or sales order files.
Alternatively, you can extract the initial build schedule from existing purchase orders and jobs for MPS items and then use the Build Schedule Maintenance program to amend the records as required to create a viable initial schedule.
Toolbar Options
| Field | Description |
|---|---|
| Start Processing | Creates the demand file according to the options selected. |
|
This prints the information currently displayed in the listview, Report or output pane. |
|
| Save Form Values |
This option is only enabled in Design mode (Automation Design).
Your selections are saved and applied when the program is run in automated mode. Form values and defaults are applied at operator level (i.e. they are not saved at role or group level). |
Information
| Field | Description | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Processing options | |||||||||||
| Extract selection |
|
||||||||||
| After processing completed |
These options are displayed within programs that can be automated. They let you indicate the action you want to perform once processing is complete. |
Report
This pane displays the results of the processing function you selected once processing is complete (unless you selected the option to close the application from the After processing completed section).
Processing sequence
-
If the build schedule file already exists, then it is removed.
-
If forecasts have been selected, then the program extracts the following:
- All MPS items. These are directly written into the build schedule.
-
All planning bill items. For these items all first level components are checked to locate any MPS items. If any are found, then their quantities are converted as follows:
A = (B x C) + [(B x C) x D] + E
Where:
- A indicates the quantity required
- B indicates the quantity per
- C indicates the forecast of planning bill part
- D indicates the scrap %
- E indicates the scrap quantity
This figure is then rounded up to the maximum number of decimals for the item (Stock Codes).
-
If sales orders have been selected, then the program extracts existing sales order for MPS items and converts the sum of the ship quantity and back order quantity into the stocking unit of measure, before creating a build schedule record.
Sales orders in D - Draft status are excluded. Only orders in an active status contribute to the build schedule. A Draft order carries no committed demand and must not create a build schedule record. -
If purchase order and jobs have been selected, then the program extracts all incomplete jobs and outstanding purchase orders for MPS items. The quantity still to be manufactured (from Work in Progress) and the quantity still to be received into stock (from Purchase orders) is written to the build schedule record.
The Date Required field is generated from the date of supply (job delivery date or purchase order due date) or date of demand (forecast date or sales order due date).
The stock item's dock-to-stock and the entry made at the Days after stock arrival it can be used option (Requirements Planning Setup) are added (if created from supply) or subtracted (if created from demand) to arrive at the build schedule date.
Notes and warnings
Warning messages
-
If the build schedule already exists, a warning message is displayed requesting you to confirm the deletion of the exiting build schedule before you can continue.
Exclusions
-
All items on Sales orders and Purchase orders excluded from the MRP calculation at Order Header level are ignored by this program (irrespective of their inclusion at line level).
Individual Sales order and Purchase order lines excluded from the MRP calculation at line level are ignored by this program for orders included at Order Header level.
-
Sales orders in D - Draft status are excluded from the build schedule extraction. A draft order must not drive the master production schedule until it is released to an active status, otherwise it would generate incorrect suggested production orders and purchase requisitions.
eSignature considerations
Electronic Signatures provide security access, transaction logging and event triggering. This enables you to increase control over your system changes.
Access to the following eSignature transactions within this program can be restricted at Operator, Group, Role or Company level. You configure this using the eSignature Setup program.
| eSignature Transaction | Description |
|---|---|
| MRP Initial build extract |
Controls access to the Start Processing function in the Initial Build Extract program. |
Password considerations
Password access to the following functions in this program may be defined in the Password Definition program. When defined, the password must be entered before you can access the function.
| Field | Description |
|---|---|
| MRP Initial build schedule extract | This password restricts access to the Processing options within the Initial Build Extract program. |